Project Schedules
May - July 2000 | Aug - Sept 2000 | Oct - Dec 2000 | Jan - Aug 2001
Schedule May, 2000 - July, 2000
Updated July 31, 2000
Date
Task
Who
Where
Week of May 8
5/11
2. Technical Team meeting: ImageServer discussion.
The Teams
UConn
Week of May 15
5/18
Visit Boston Photo Imaging.
5/22
Hired a lesson plan writer.
CHS
Week of June 5
6/8
Technical Committee meeting: 1. JPEG Image specifics. 2. ImageServer issues.
Technical Team
Week of June 12
DLI2 Conference (Tom, Jim, Allison)
.
Week of June 19
6/20
2 pm: Boston Imaging visit UConn.
CHS staff
UConn staff
6/21
Finalize cataloging fields.
Catalogers
Week of June 26
6/28
Cataloger training for GIS component & ImageServer.
Patrick & Catalogers
6/29
One lesson plan topic selected.
Edu. Team Patrick Flynn
6/30
100 images from each site selected.
Selection
UConn 100 images delivered to CHS.
Week of July 3
7/6
Boston Imaging on site filming.
7/7
Cataloging fields given to Fritzi. (Delayed)
Allison
Week of July 10
7/10
9:00 am All project staff meeting (cancelled)
Everybody
Mystic
Mystic 100 images delivered to CHS.
Mystic staff
Finalize subject headings.
7/14
300 Images conversion done.
All Sites
ImageServer template setup. (Delayed)
Fritzi
Week of July 17
Start cataloging pilot images. (Delayed)
All sites
One Lesson Plan (draft) written.
Patrick Flynn
Week of July 24
7/28
Draft Web site up (Delayed)
Week of July 31
UConn 3,500 images ready for shooting.