CHO Phase II Project Outline Summer 2003


Project Start Date: Thu 5/1/03
Project Finish Date: Fri 8/29/03

Tasks with Assignments

ID
Task Name
WorkDurationStartFinish% Work Complete
1
Digitization with Boston Photo Imaging
0 hrs44 daysMon 5/12/03Thu 7/3/030%
2
Subtasks from Mary Anne
0 hrs44 daysMon 5/12/03Thu 7/3/030%
3
Preparation of Mapping and CHO Phase I Records for Migration to ENCompass
0 hrs20 daysWed 5/7/03Fri 5/30/03100%
4
Confirm MARC to Dublin Core Fields for Mapping
0 hrs11 daysMon 5/12/03Fri 5/23/03100%
5
Rework Existing Document on MARC to Dublin Core Mapping
0 hrs3 daysWed 5/21/03Fri 5/23/03100%
6
Clean-up Records for CHO Phase I
0 hrs20 daysWed 5/7/03Fri 5/30/03100%
7
Define Data Configurations and Structure for CHO Phase I Repository in ENCompass
0 hrs1 dayWed 5/7/03Wed 5/7/03100%
8
Name Repository for Photographic Materials
0 hrs1 dayWed 5/7/03Wed 5/7/03100%
9
Confirm Use of Qualified Dublin Core as the Base DMD
0 hrs1 dayWed 5/7/03Wed 5/7/03100%
10
Determine Required Descriptive Metadata Elements
0 hrs1 dayWed 5/7/03Wed 5/7/03100%
11
Determine Name and Number of Desired Containers in Repository
0 hrs1 dayWed 5/7/03Wed 5/7/03100%
12
Confirm Format for and Use of Technical Metadata in Repository
0 hrs1 dayWed 5/7/03Wed 5/7/03100%
13
End Data Entry/Modifications for CHO Phase I Content
0 hrs0 daysFri 5/30/03Fri 5/30/03100%
14
Set-up ENCompass Clients at Partner Sites and Make Documentation Available
0 hrs47.86 daysWed 5/7/03Thu 7/3/030%
15
Migrate Data from CHO Phase I Database into ENCompass
0 hrs15.86 daysMon 6/16/03Thu 7/3/030%
16
Complete Initial Data Extraction for CHO Phase I Database (Endeavor's Server)
0 hrs5.57 daysMon 6/16/03Fri 6/20/030%
17
Review Initial Data Extraction and Make Comments/Revisions
0 hrs5.57 daysMon 6/23/03Fri 6/27/030%
18
Create Data Configurations and Build Data Structure for CHO Phase I Repository in ENCompass
0 hrs5 daysMon 6/23/03Fri 6/27/030%
19
Complete Official Data Migration for CHO Phase I Database (UConn's Server)
0 hrs4 daysMon 6/30/03Thu 7/3/030%
20
New CHO Phase II Project Manager Begins Work
0 hrs0 daysMon 6/23/03Mon 6/23/030%
21
Hire Catalogers
0 hrs45.71 daysWed 5/7/03Tue 7/1/030%
22
WebVoyage Upgrade to Version 2001.2---CHO Website Unavailable
0 hrs4 daysTue 7/8/03Fri 7/11/030%
23
Complete ENCompass Training at UConn
0 hrs5.57 daysMon 7/21/03Fri 7/25/030%
24
Define Data Structure for CHO Phase II Repositories in ENCompass
0 hrs10.14 daysWed 7/23/03Mon 8/4/030%
25
Determine Number and Names of Repositories Needed
0 hrs10.14 daysWed 7/23/03Mon 8/4/030%
26
Determine DTDs for Each Repository
0 hrs1 dayWed 7/23/03Wed 7/23/030%
27
Determine DTD Configurations for Each Repository
0 hrs1 dayWed 7/23/03Wed 7/23/030%
28
Build Data Structure for CHO Phase II Repositories
0 hrs14.71 daysMon 8/4/03Thu 8/21/030%
29
ENCompass Upgrade to Version 3.5
0 hrs0 daysFri 8/1/03Fri 8/1/030%
30
Work on OAI Framework
0 hrs23.86 daysFri 8/1/03Fri 8/29/030%